Engineering
Public Service Project Information
Recent Projects
Annual Waterline Replacement – Starr Avenue Addition
This design effort will evaluate potential alignments for the new waterline to ensure reliable service and improved system performance. Field crews may be seen in the project area during this phase as data collection and site evaluations take place.
The project area includes:
- Seaman Road: from the west corporation limit to Berlin Avenue
- Wheeling Street: from Seaman Road to Starr Avenue
- Berlin Avenue: from Seaman Road to Starr Avenue
- Whittlesey Avenue: between Seaman Road and Starr Avenue
- Additional streets: Edwin Street, Mechanic Street, Portland Street, Arthur Street, Hayden Street, Bleeker Street, and Northvale Drive
(Please see the attached site map for reference.)
Construction is tentatively scheduled for 2026–2027.
If you have any questions regarding this project, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Limited Environmental Review and Finding of No Significant Impact
City of Oregon – Lucas County
Water Line Replacement – Starr Avenue Addition
Loan number: FS390721-0032
Sidewalk and Curb Ramp Improvement Project PY 2024 CDBG Allocation Program
The proposed work consists of the replacement of curb ramps in the East Hampton, Beachwood Estates, Hallmark Square, and Moundview Subdivisions. The work items shall also include concrete removal and replacement, grading, seeding, and restoration. Construction is planned to start the week of July 22, 2026, and should be completed by August 21, 2026.
The contractor for the project is RMH Concrete & Foundations, Inc., 4433 West Collins Road, Collins, Ohio 44826. After the curb ramp installation, the contractor will be responsible for backfilling and reseeding any disturbed areas prior to the completion of the project.
Corduroy Road Residential Wastewater Infrastructure Study
The City of Oregon, in partnership with the Toledo-Lucas County Health Department, is conducting a residential wastewater infrastructure study along Corduroy Road between the addresses of 6010 and 7055. This study is intended to better understand potential sources of bacterial contamination affecting local waterways and Maumee Bay State Park lakeshore beaches.
Be sure to check back for updates as the study progresses.
Public Meeting
Invitation to Public Meeting (May 22, 2026)
Meeting Presentation (June 9, 2026)

(This map displays E. coli sampling results collected within the Corduroy Road HSTS Study Area. Several locations exceeded EPA advisory and closure thresholds. The map includes study area boundaries, streams, and sewer infrastructure.)
Background
This study is part of ongoing efforts to improve water quality within the Wolf Creek/Berger Ditch watershed and reduce bacterial contamination that has contributed to beach advisories and closures at Maumee Bay State Park.
Water quality studies conducted since the early 2000s have identified elevated levels of E. coli bacteria within the watershed. Household Sewage Treatment Systems (HSTS), commonly known as septic systems, as well as properties without access to sanitary sewer service, may be contributing to these elevated bacteria levels.
Scope
The Toledo-Lucas County Health Department will conduct inspections of approximately 61 residential septic systems within the study area. The purpose of these inspections is to identify potential sources of human-related bacterial contamination entering local waterways.
The assessment will help determine:
- Whether individual septic systems are functioning properly or failing.
- Whether cross-connections or illicit connections exist.
- The extent to which wastewater infrastructure issues may contribute to bacterial contamination.
- Appropriate corrective actions and long-term solutions, including; septic system repairs, system replacements or sanitary sewer installation.
Community Participation
Community involvement is an important part of this study. Residents are encouraged to contact the Toledo-Lucas County Health Department to learn more about the assessment process and to schedule a septic system inspection appointment.
Toledo-Lucas County Health Department – (Phone) 419.213.4100 Option 4
Questions or Concerns?
If you have any questions or concerns regarding this study, please feel free to contact the Department of Public Service at 419.698.7047 or eng@oregonohio.org
2026 Roadway Improvement Program
Road Program Council Memo (3-16-26)
Be sure to check back for updates as the projects progress.
Project #1: Holly Drive Reconstruction
Location: Starr Ave and Eastmoreland Dr (Area 1) and Eastmoreland Dr and Luverne Ave (Area 2)
Contractor: E. R. Zeiler Excavating Inc.
Award Amount: $635,447.00
Project #1 Location Area 1 Map
Project #1 Location Area 2 Map
Construction Notice Letter (June 3, 2026)
Road Closure Notice (August 21, 2026)
Project #2: Springwood Drive South and East Reconstruction
Location: Springwood Dr West to Springtime Drive
Contractor: Crestline Paving
Award Amount: $428,588.30
Project #1 Location Area 2 Map
Construction Notice Letter (June 3, 2026)
Road Closure Notice (August 21, 2026)
Questions or Concerns?
If you have any questions or concerns regarding these projects, please feel free to contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org
Navarre Avenue Safety Improvement Project (LUC-2-21.72 - PID 118234)
In August 2025, the City of Oregon awarded a contract to Hillabrand & Sons Construction in amount of $6,079,347.45 (5811 Woodville Road, Northwood, Ohio 43619) for the Navarre Avenue Safety Improvement Project. The project will implement a variety of safety improvements along Navarre Avenue (SR 2) between Isaac Streets Drive and Coy Road, with the goal of reducing crashes and improving overall safety for motorists, pedestrians, and nearby businesses.
Construction Schedule:
- February 2026: Preliminary underground work related to traffic signals begins.
- April 2026: Roadway construction begins.
- October 2026: All construction activities are expected to be complete.
The project extends from Isaac Streets Drive to just east of Kroger Drive (approximately 500 feet west of Coy Road). All work will occur within existing public rights-of-way or easements along Navarre Avenue.
Funding
Eligible elements of the project are partially funded through the following sources:
- ODOT Highway Safety Improvement Program: $5,000,000
- ODOT Urban Paving Program: $600,000
- Ohio Public Works Commission: $592,682
Planned Improvements:
- Construction of a center median
- New traffic signals at Harbor Drive, Kingston Court/Planet Fitness, and Kroger Drive, including ADA-compliant pedestrian signals and U-turn bulb-outs
- Roadway resurfacing and updated pavement markings
- Overhead lane-use signage
- Landscaping and streetscape enhancements consistent with the Navarre and Wheeling project
Traffic and Access:
- Periodic lane closures will occur, but at least one lane in each direction will remain open at all times.
- Median installation and paving work will be scheduled during off-peak and nighttime hours.
- Driveway access will be maintained except during active construction directly in front of a driveway. Alternative arrangements will be coordinated with affected property owners in advance.
- Project representatives will contact stakeholders directly regarding any potential access restrictions.
Project Oversight:
The City has retained American Structurepoint, Inc. (ASI), 600 Superior Avenue East, Suite 2401, Cleveland, Ohio 44114, to provide a full-time project representative and inspector. The inspector will be onsite throughout construction to address any questions or concerns.
If you have any concerns or questions regarding this project, please contact the City of Oregon Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
LUC-Starr Avenue Reconstruction and Resurfacing (PID 117122)
- Resurfacing portion:
- 0.53 miles of Starr Avenue from Earlwood Avenue to Whittlesey Avenue
- 0.17 miles of Wheeling Street from Northvale Drive to Randall Drive
- Reconstruction portion:
- 0.10 miles of Starr Avenue from the west corporation limit to Earlwood Avenue
Construction Notice Letter (June 25, 2026)
Road Closure Notice (June 25, 2026)
Resurfacing & Lane Closure Notice (September 30, 2026)
Resurfacing work will include:
- Milling approximately 3 inches of existing asphalt
- Roadway asphalt concrete base and joint repairs as needed
- Two-course asphalt overlay over the project limits
Reconstruction work will include:
- Full reconstruction from west corporation limit to Earlwood Avenue
- Installation of new aggregate base, underdrains, and curbing
Additional improvements:
- Drainage upgrades
- ADA-compliant curb ramps
- Adjustment of manholes
- Updated signage and pavement markings
- Other related work as necessary
Construction Schedule:
- February 2026: Project Award
- July 2026: Roadway construction is anticipated to begin.
- Late October 2026: All construction activities are expected to be complete.
Funding
Eligible elements of the project are partially funded through the following sources:
- TMACOG Surface Transportation Block Grant (STBG) Program: $500,000
- Ohio Public Works Commission: $600,000
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
LUC- Corduroy Road Bridge Replacement (PID 119725)
Road Closure Notice (September 30, 2026)
Construction Schedule:
- February 2026: Project Award
- June 2026: Construction is anticipated to begin.
- October 2026: All construction activities are expected to be complete.
Funding
Eligible elements of the project are partially funded through the following source:
- ODOT Municipal Bridge Program: $817,377 for Construction
- Design Phases: The preliminary and detailed design phases were fully funded through an ODOT Task Order at no cost to the City
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
LUC- Oregon Trail Bikeway Phase 5 (PID 121105)
Project Overview
The project involves constructing roughly 1 mile of 10-foot-wide shared-use path, composed of concrete and asphalt, primarily within the Dustin Road right-of-way. The path will extend from just east of East Harbor Drive near the Oregon Town Center area along Dustin Road to Navarre Avenue, ending at the ALDI intersection.
Construction Notice (May 26, 2026)
Construction Notice (June 9, 2026)
Project Connectivity
The Oregon Trail Bikeway Phase 5 will connect planned commercial and residential development at the Oregon Town Center area to the existing Oregon Bikeway Network and will serve as part of a potential future connection to the City of Northwood. The Oregon Bikeway Network provides access to Maumee Bay State Park, Clay High School, the Oregon Municipal and Recreation Complex, Pearson Metro Park, Starr Elementary School, and Fassett Junior High School.
Construction Schedule:
- March 2026: Project Award
- May / June 2026: Construction is anticipated to begin.
- October 2026: All construction activities are expected to be complete.
Funding
Eligible elements of the project are partially funded through the following sources:
- TMACOG Transportation Alternatives (TA) Grant: $400,000
Path Segments
- Dustin Road (East Harbor Drive to Coy Road)
- 10-foot-wide concrete shared-use path along the south side of Dustin Road
- Replaces existing 5-foot sidewalk
- Fills in missing sidewalk gaps to provide a continuous facility
- Dustin Road Paper Street (East of Coy Road)
- 10-foot-wide asphalt shared-use path
- Constructed within the Dustin Road paper street right-of-way
- Includes drainage improvements (drainage tiles and catch basins)
- Crosses Schmidlin Road
- Utilizes short segments of existing low-volume Dustin Road roadway to connect sections of the new path up to Coy Road
- Schmidlin Place Subdivision
- 10-foot-wide asphalt shared-use path
- Located within existing City right-of-way
- Runs north–south along the east property line of the Schmidlin Place Subdivision and the west property line of the Dairy Depot property
- Includes drainage improvements (drainage tiles and catch basins)
- Navarre Avenue Connection
- 10-foot-wide concrete shared-use path along the south side of Navarre Avenue
- Connects to the existing shared-use path in front of ALDI
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
LUC–Pickle Road Path & Sidewalk Safe Routes to School (SRTS) Project – PID 124618
Project Description
The City of Oregon proposes to construct new sidewalks and a shared-use path along Pickle Road to improve pedestrian and bicycle safety for students traveling to nearby schools. This project will help create safer connections between surrounding neighborhoods, existing bike trails, and local schools, encouraging students to walk or bike to school.
The proposed improvements will provide safer access to Coy Elementary School and Cardinal Stritch Catholic High School and Academy. These improvements are recommended in the City of Oregon’s Safe Routes to School Travel Plan, which identifies infrastructure needs to support safer and more convenient walking and bicycling routes for students and the community.
Proposed Improvements
Sidewalk Construction
Approximately 3,700 linear feet of 5-foot-wide sidewalk will be constructed along Pickle Road in several segments to close existing gaps in the pedestrian network. Proposed sidewalk locations include:
- North side of Pickle Road: Town Center Boulevard to Laura Lane
- South side of Pickle Road: YMCA to Eastland Drive
- North side of Pickle Road: Oregon Trail Bike Path to Heritage Lane
- South side of Pickle Road: Oregon Trail Bike Path to Oaktree Court
Shared-Use Path Construction
The project will also construct 1,410 linear feet of a 10-foot-wide asphalt shared-use path designed to accommodate both pedestrians and bicyclists. This path will provide a direct connection between Coy Elementary School and the Oregon Trail Bike Path, expanding access to the regional trail network.
Project Benefits
The proposed improvements will:
- Increase safety for students walking and bicycling to school
- Close critical gaps in the sidewalk network along Pickle Road
- Improve connectivity between neighborhoods, schools, and the regional bike trail system
- Support the goals of the City of Oregon’s Safe Routes to School program
Project Schedule:
- 2026: Detailed Engineering Design
- 2027: Easement Acquisitions
- 2028: Construction
Funding
Eligible elements of the project are partially funded through the following source:
- ODOT Safe Routes to School Grant: $500,000
Project & Survey Notice (4-9-2026)
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Wheeling Street Sidepath Project (LUC MR 2189 0.272 Wheeling Street Shared Use Path) – PID 124195
Project Overview
This project consists of constructing approximately 0.72 miles of an 11-foot-wide asphalt shared-use path along Wheeling Street. The proposed path will extend from Brown Road to Interstate 280 and from the driveway between Mercy Health – Bay Park Hospital and Meijer to the City of Oregon’s southern corporation limit.
Between these two segments, the proposed shared-use path will connect to an existing 8-foot-wide concrete path that is part of the shared-use path network located on the campus of Mercy Health – Bay Park Hospital.
Currently, a 5-foot-wide sidewalk exists along these portions of Wheeling Street and accommodates a significant amount of both pedestrian and bicycle traffic. However, the sidewalk was not designed for shared use and provides limited space for pedestrians and bicyclists traveling in opposite directions, which can lead to user conflicts. To address this issue, the project will replace the existing sidewalk with an 11-foot-wide asphalt shared-use path designed to safely accommodate pedestrians, bicyclists, and other non-motorized users. The wider facility will improve safety, increase capacity for active transportation, and provide a more comfortable and accessible route for users of all ages and abilities
The project will also improve connectivity along the Wheeling Street corridor by linking multi-family residential areas, commercial destinations, and healthcare facilities, including Mercy Health – Bay Park Hospital and Meijer, while enhancing the City of Oregon’s overall pedestrian and bicycle transportation network.
Project Schedule:
- 2026: Detailed Engineering Design
- 2027: Construction
Funding
The construction elements of the project are fully funded through the following source:
- ODOT Safety Grant Funding: $ 441,592 (100% covered, with no local match required up to the grant amount)
The City of Oregon will manage the project design using in-house engineering staff, reducing costs and ensuring local oversight throughout the planning and design process.
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
LUC-Bay Shore Road & Otter Creek Road Roadway Departure Improvements (PID 123994)
The City of Oregon will be implementing roadway departure countermeasures at the long sweeping curve at Bay Shore Road and Otter Creek Road.
Countermeasures will include:
- Edge and centerline rumble strips
- Enhanced curve signage with dynamic flashing chevrons
- Raised pavement markers
- Updated road striping
The bid specifications also include an alternate bid for adding rumble strips on selected curves along the relocated Cedar Point Road. Depending on bid results and available budget, the City will determine whether to proceed with the Cedar Point Road improvements.
Construction Schedule:
- February 2026: Project Award
- June 2026: All construction activities are expected to be complete.
Funding
Eligible elements of the project are partially funded through the following source:
- ODOT Highway Safety Improvement Program (HSIP) Grant: $91,300
Background
- Multiple roadway departure crashes over the past five years.
- Roadway departure crashes occur when a vehicle crosses the edge or center line, leaves the travel lane, and strikes a fixed object, overturns, or enters a ditch.
- Crash Data (2019–2023):
- Average of ~2 roadway departure crashes per year.
- One fatal crash in 2023.
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Sanitary Sewer Rehabilitation Project, Phase 3 Part B
Project Scope
The project includes:
- Inspection and lining of existing sanitary sewers, sewer laterals, and sewer manholes within the public right-of-way in the Eastmoreland 2nd Extension and Starr Avenue Addition to Toledo subdivisions.
- Excavation point repairs of failed sanitary sewer connections.
- Installation of two new sanitary sewer manholes.
See below project description and maps for details.
Construction Notice Letter (10-31-25)
Construction Update Notice (2-10-26)
Background
Since 2008, the City of Oregon has implemented an Inflow/Infiltration (I/I) Reduction Program to reduce excessive rainwater and groundwater entering the sanitary sewer system, which can cause:
- Sanitary sewer overflows
- Basement backups
- Wet weather bypasses at the wastewater treatment plant (WWTP)>
Through a variety of sewer improvement projects—including traditional replacements and cured-in-place lining of existing sewers—the I/I Reduction Program has reduced the number and severity of these issues. Phase 3, Part B continues this effort in the Wheeling Street Sanitary Sewer District, east of Wheeling Street.
Project Details
- Sewers in the project area are approximately 85 years old.
- Rehabilitation will include lining 8-inch, 12-inch, and 15-inch pipes using a cured-in-place lining (CIPP) method. This method uses a resin-impregnated fabric, steam-cured inside the existing sewer, creating a new pipe within the old pipe.
- The project also includes:
- Lining 130 sanitary sewer laterals and 28 sanitary sewer manholes
- Excavation and pipe repair of 11 deteriorated chimney riser connections
- Installation of 3 new sanitary sewer manholes
- Repair of storm sewer and associated restoration
Construction Impact
Most work occurs within existing sewer pipes, so disruptions will be minimal. Residents may notice:
- Contractor vehicles on neighborhood streets (jet/vac trucks, CCTV camera trucks, box trucks)
- Temporary driveway closures on Randall Dr. and Berlin Ave. for up to one day during sewer excavation and repair. Residents will be notified in advance.
Funding and Environmental Review
This project is funded by a reduced-interest loan from the Ohio EPA’s DEFA Water Pollution Control Loan Fund (WPCLF). The Ohio EPA has released a Limited Environmental Review and Finding of No Significant Impact for the project.
Eastmoreland Drive Storm Sewer Replacement - 2025
Due to the age and condition of the existing storm sewer on Eastmoreland Drive, the City of Oregon is planning a replacement of the pipe. This is for the section of storm sewer between S. Wheeling Street and S. Berlin Avenue. As stated in the letter to residents, unfortunately, nine (9) trees will need to be removed for this work. These are the trees located in the center of the boulevard. The trees along the sidewalks and roadside will not be affected. The trees were planted directly on top of the storm sewer and have contributed to the condition of the pipe. Future tree plantings are planned and will be more strategic in placement, avoiding underground utilities to the best extent possible.
It is important to note that this is a critical segment of the storm sewer system for this area. This sewer not only serves Eastmoreland Drive, but also S. Wheeling Street, Randall Drive, S. Berlin Avenue, Gladhaven Drive, and S. Whittlesey Avenue. If this pipe were to completely fail and collapse, many streets and homes could be flooded during a rain event.
As shown in the below images from the pipe inspection video, the condition of the pipe is extremely poor. Cracks and fractures are seen throughout. There are also several segments that have missing pipe sections where dirt is visible and has already been washing into the sewer. This is causing the sinkholes seen on the surface in the blvd area. The storm sewer is beyond its useful life and is in need of replacement.
The City is anticipating finalizing the design of the project over the month of May and advertising for construction bids soon after. Construction will likely take place over the summer (2025). The letter and map in the links below further describe the project and show the project area. Please contact the Department of Public Service at 419-698-7047 if you have any questions on this project.

Offset joints in storm sewer are causing sinkholes in the Blvd area

Multifracture segment of pipe in Eastmoreland Dr Storm Sewer

Debris from sinkhole above filling storm sewer

Tree directly on top of storm sewer, Eastmoreland Dr.

Sinkholes in the Blvd from storm sewer condition

Storm Sewer alignment in the Blvd impacted by tree plantings.
2025 Roadway Improvement Program
Project #1: Eastmoreland Drive North Roadway Reconstruction
Location: S Edward St to S Coy Rd
Contractor: Ebony Construction Co. Inc
Award Amount: $509,396.78
Construction Notice Letter (6-30-25)
Project #2: Springwood Drive West Roadway Reconstruction
Location: Springwood Dr S to Terminus
Contractor: Crestline Paving
Award Amount: $354,927.05
Construction Notice Letter (6-30-25)
Construction Update (7-31-25 Final)
Project #4: Navarre Avenue Pavement Repairs (Waterline & Utility Patches)
Location: S Coy Rd to S Lallendorf Rd
Contractor: Henry W. Bergman, Inc.
Award Amount: $37,230.00
Project #5: Oregon Trail Multi-Use Path – Phase 2
Location: Navarre Ave to Starr Ave
Contractor: Vernon Nagel Inc
Award Amount: $591,253.00
Construction is expected to begin in late June or early July. Be sure to check back for updates as the projects progress.
Road Program Award Memo (5-29-25)
Questions or Concerns?
If you have any questions or concerns regarding these projects, please feel free to contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Otter Creek Stream and Floodplain Restoration Project – 2024
Construction of the Otter Creek Stream and Floodplain Restoration Project – 2024 is set to begin on October 7th, 2024. In August of 2024, the City of Oregon awarded a contract to Haynes Construction, Inc of Norwalk, Ohio for the Otter Creek Stream and Floodplain Restoration Project – 2024. The work involves the improvement of Otter Creek by natural channel stabilization and the creation of adjacent stream floodplains. The project is designed to improve Otter Creek and create large habitat areas for birds, fish, and amphibians. Over 2,500 linear feet of streambank will be stabilized using natural channel design methods including live stakes, locked logs, and replanting with native grasses and shrubs to hold soils. This vegetation will reduce streambank erosion during large rain events. Other proposed work includes:
- Streambank stabilization by grading, live stake planting, and the utilization of rootwads on 2,500 linear feet of Otter Creek streambank
- Establishment of instream habitat structures such as rock riffles and cover stones for fish habitat
- Reestablishment of the connection of Otter Creek to 2.5 acres of floodplain
- Enhancement of 2.5 acres of Otter Creek floodplain using grading, microtopography, and wetland, shrub, and tree plantings
- Enhancement of 4 acres of existing wetland and riparian area adjacent to the creek using wetland, shrub, and tree plantings and grading.
- Diversion of 53 acres of stormwater drainage to proposed floodplains to reduce sediment and nutrients prior to discharge to Otter Creek
- A proposed walking path within the project area to provide additional passive recreation and wildlife viewing opportunities.
In August of 2022, the City of Oregon was awarded a grant in the amount of $1,389,510 from the US EPA GLNPO office for this project. The grant included funding for property acquisition, engineering and design, and construction of these improvements.
Stay tuned to this webpage for construction updates and project pictures as the work proceeds.

Otter Creek flows Northeasterly through the Project Site

Existing Otter Creek – near N Yarrow Street

Existing Streambank Erosion – Otter Creek near Taylor Road
Progress update photos as of 1/30/2025

The Otter Creek Stream and Floodplain Restoration Project is nearing completion.
The contractor is completing the landscaping work this week. Landscape work includes the planting of the following:
- 1.0 acre of pollinator upland seed mix
- 4.5 acres of wetland seed mix
- 418 – Bare Root Native Trees
- 629 – Bare Root Native Shrubs
- 1,635 – Native Live Stakes
- 15 – 1.5” Caliper Native Trees
Once planting is completed, a few touch up items will be performed and the walking path will be opened.
Please feel free to contact the Department of Public Service if you have any questions about this project.







Coy Road Resurfacing and Widening (LUC CR 556 1.83 PID 116040)
The City of Oregon has awarded a contract to The Shelly Company, 1700 Fostoria Avenue, Suite 200, Findlay, OH 45840 to resurface and add paved shoulders to approximately 1.4 miles of Coy Road between Fleitz Drive and Seaman Road, excluding the section between Worden Road to 250’ North of Navarre Avenue. The project will also include adding missing sidewalk segments along the west side of Coy Road from AutoZone to Seaman Road and resurfacing approximately 800 ft of Pickle Road east and west of Coy Road.
The City has received grant funding from the Toledo Metropolitan Area Council of Governments (TMACOG) Transportation Improvement Program through the Ohio Department of Transportation (ODOT) for the project.
The project will consist of milling approximately 3” of the existing asphalt surface throughout the project limits. The pavement will then be widened from approximately 27’ wide to approximately 32’ wide to accommodate a paved asphalt shoulder on both sides of the roadway. Following the shoulder widening, a two-course asphalt overlay will be placed over the entire project limits. The project will also include drainage work, sidewalk, ADA curb ramps, adjustment of manholes, signage, pavement markings, and related work, as necessary.
Construction on the project is anticipated to begin Tuesday, September 3, 2024, weather dependent. The contractor plans to maintain one lane of traffic thru the work zone area by use of flaggers or portable traffic signals. If road closures are required additional notices will be provided. The project is scheduled to be substantially completed by early November.
If you have any questions regarding this information, please contact the Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Water Line Replacement Program - Seaman Road, Norden Road, and Wynn Road
The City of Oregon has awarded a construction contract for the Seaman Road, Norden Road, and Wynn Road Waterline Replacement. Construction work is scheduled to begin in June 2024 and should be completed by April 2025.
The project improvements will occur within the existing public right-of-way or established easements with the following work occurring between these addresses:
SEAMAN ROAD
5011 Seaman (Intersection of Wynn and Seaman) – 5247 Seaman
Installation of a new 8-inch waterline along the north side of Seaman Road including new fire hydrants.
5260 – 5808 Seaman Installation of a new 8-inch waterline along the south side of Seaman Road including new fire hydrants.
5808 – 7435 Seaman (Intersection of N. Curtice Road and Seaman Road)
Installation of a new 8-inch waterline along the north side of Seaman Road including new fire hydrants.
WYNN ROAD
5011 Navarre (Intersection of Wynn and Navarre) – 437 S. Wynn
Installation of a new 8-inch waterline along the east side of Wynn Road including new fire hydrants.
Intersection of Starr and Wynn – Intersection of Starr Extension and Wynn
Installation of a new 8-inch waterline along the west side of Wynn Road including new fire hydrants. This section will be installed with a bore and jack method.
166 Lawai – 5002 Seaman Road (Intersection of Wynn and Seaman)
Installation of a new 8-inch waterline along the west side of Wynn Road including new fire hydrants.
NORDEN ROAD
Intersection of Norden and Navarre – 341 S. Norden
Installation of a new 8-inch waterline along the east side of Norden Road including new fire hydrants.
109 S. Norden – Intersection of Norden and Corduroy
Installation of a new 8-inch waterline along the east side of Norden Road including new fire hydrants.
Following all required testing, the existing water services serving all properties within the project limits will be connected to the new waterline as part of this project.
Construction plans and specifications for the project are available for review at the City of Oregon Municipal Complex at the Department of Public Service Office.
If you have any concerns or questions regarding this project, please contact the City of Oregon Department of Public Service at (419) 698-7047.
Limited Environmental Review and Finding of No Significant Impact
City of Oregon – Lucas County
Water Line Replacement Program – Seaman Road, Norden Road, and Wynn Road
Loan number: FS390721-0029
The attached Limited Environmental Review (LER) is for a drinking water distribution project in Lucas County which the Ohio Environmental Protection Agency intends to finance through its Water Supply Revolving Loan Account (WSRLA) below-market interest rate revolving loan program. The LER describes the project, its costs, and expected environmental benefits. Making available this LER fulfills Ohio EPA’s environmental review and public notice requirements for this loan program.
Ohio EPA analyzes environmental effects of proposed projects as part of its WSRLA program review and approval process. We have concluded that the proposed project should not result in significant adverse environmental impacts. This project’s relatively narrow scope and lack of environmental impacts qualifies it for the LER rather than a more comprehensive Environmental Assessment. More information can be obtained by calling or writing the person named at the end of the attached LER.
Upon issuance of this Finding of No Significant Impact (FNSI) determination, award of funds may proceed without further environmental review or public comment unless new information shows that environmental conditions of the proposed project have changed significantly.
Safe Routes to School Travel Plan Update
Oregon Safe Routes to School Travel Plan
Questions or comments regarding the Safe Routes to School Plan update should be directed to srts@oregonohio.org or the Department of Public Service at 419-698-7047.
Brown Road Sanitary Sewer Project (East of Coy Road)
Construction work on the project began in early September 2024. The contractor has indicated that final grading and seeding for the project will not be completed until all testing has been completed on the sanitary sewer. The current project completion date is November 8, 2024.
Brown Road is planned to remain open to traffic between Coy Road and Lallendorf Road throughout the construction. Due to the nature of the work, access to driveways within the project work limits will need to be interrupted during some stages of the construction operation.
Construction plans and specifications for the project are available for review at the City of Oregon Municipal Complex at the Department of Public Service Office.
Sidewalk Improvement Project PY 2022 CDBG Allocation Program
The city was awarded $150,000 in the Community Development Block Grant (CDBG) funding through Lucas County for the project. The purpose of the sidewalk project is to upgrade existing curb ramps to meet current American Disability Act (ADA) standards.
The proposed work consists of the replacement of curb ramps in the East Hampton, Beachwood Estates, and Yorktown Subdivisions. The work items shall also include concrete removal and replacement, grading, seeding, and restoration. Construction is planned to start the week of July 29th, 2024, and should be completed by August 31st, 2024.
The contractor for the project is Quinn Concrete Construction, Inc., PO Box 80065, Toledo, Ohio 43608. After the curb ramp installation, the contractor will be responsible for backfilling and reseeding any disturbed areas prior to the completion of the project.
Wynn Road and Corduroy Road Resurfacing (LUC-Wynn Road and Corduroy Road Resurfacing, PID 118110)
The project will include resurfacing 1.0 miles of Wynn Road and 1.0 miles of Corduroy Road and making necessary repairs. The project will consist of milling approximately 3” of the existing asphalt surface along the entire project limits, followed by making any necessary base repairs. Following the base repairs, a two course asphalt overlay will be placed over the entire project limits. The project will also include adjustment of manholes, signage, pavement markings, ADA curb ramps and related work, as necessary.
Construction on the project is anticipated to begin Tuesday, July 16, 2024. The contractor will begin by milling approximately 3” of the existing asphalt surface along the entire project limits, followed by making any necessary base repairs. Construction is anticipated to be completed by Friday, August 9, 2024.
Construction plans and specifications for the project are available for review at the City of Oregon Municipal Complex at the Department of Public Service Office.
If you have any concerns or questions regarding this project, please contact the City of Oregon Department of Public Service at (419) 698-7047 or eng@oregonohio.org.
Wolf Creek Stream & Floodplain Restoration Project

The City of Oregon has received two grants for this work, one from the USEPA Great Lakes National Program Office (GLNPO) and the other from the State of Ohio H2Ohio program. Grant funding totals over $1,400,000. The general contractor for the project is Geo. Gradel Co., 3135 Front Street, Toledo, Ohio 43605. The plans and specifications were prepared by The Mannik & Smith Group, Inc., 1800 Indian Wood Circle, Maumee, Ohio 43537.
The project site is on the southside of the Oregon Recreation Complex, located at 5401 Starr Avenue Extension. This site provides an excellent opportunity for the public to view a stream and floodplain restoration project and learn about its benefits for water quality and Lake Erie. This area is a priority project for aquatic habitat restoration because of its location within the Maumee Area of Concern.
Drone Video of Near Completed Project (8-1-24)
Drone Video of Construction (12-14-23)
Drone Video of Construction (11-03-23)
Once the site is at final grade, over 16 acres will be seeded to native wetland and upland plant species. There will also be over 1,600 individual trees and shrubs and 1,250 individual wetland plugs that will be planted within the floodplain areas. Example tree species include swamp white oak, burr oak, eastern redbud, and shagbark hickory. Example wetland species include swamp milkweed, fox sedge, common rush, New England aster, and blue vervain.
Portions of the bike path through the recreational complex will be rerouted while the project is being constructed.
Work is expected to continue through Spring 2024.









Cooper Gensler, an Eagle Scout Candidate from Troop 2, is working with us to perform the “live staking” to quickly establish vegetation within the newly created stream wetland/floodplain areas as part of his Eagle Scout project. Cooper and other members of Troop 2 are harvesting “live stakes” from existing stands of willow and dogwood and then transplanting these “live stakes” into the wetland/floodplain areas.

Approximately 275 willow stakes were planted by Troop 2 on Sunday, November 5th, 2023 in the North floodplain area of the Wolf Creek east of the skate park. They also harvested approximately 200 additional dogwood live stakes for a future planting. These “live stakes” should start growing and adding immediate habitat value in the Spring of 2024.


Northwood-Oregon Bike Plan
The cities of Oregon and Northwood collaborated to develop a Bike Plan that would assess how best to connect bicycle facilities between the two communities and to adjacent jurisdictions and their bike facilities.
Oregon and Northwood have been expanding bike and pedestrian facilities in their communities over the past several years and have been proactive in conducting various plans, studies, and passing resolutions to work towards improving non-motorized facilities within their communities.
The Northwood-Oregon Bike Plan summarizes all of the existing bike facilities that have been constructed over the years to provide access to neighborhoods, parks, recreational areas, schools, public facilities, and commercial/retail areas within the communities via active transportation. The bike plan also identifies needed improvements to complete gaps in the bike facility network and to coordinate connectivity between both Northwood and Oregon, as well as adjacent jurisdictions.
Address
5330 Seaman Road
Oregon, OH 43616
Phone
419-698-7047
Fax
419-691-0241
Hours
8:00am - 4:30pm
Monday - Friday
Message Us


